Sorry folks, a bit of a delay for an update on weeks 33-39!
Very little productive activity happened over these 2 weeks (33-34). The sparkie pretty much got as far as he could with first fix and the insulation was fitted to most areas also. Stuck now before we can move onto plasterboard and further internal works as we need to get the big roof glazing sorted and fully watertight. Big shocker as AC Yules have gone into administration this week so we're struggling to find a structural glass supplier in Scotland who can meet our needs!! See photos - builder was playing around with the construction of the glazed hall (wk34) to see how best to construct the wooden support beams and position the glass.
 |
A temporary door into the main extension! |
 |
Trying to show where support beams would be positioned |
 |
View of the front door area - not sure if we're having a glass overhang yet |