I'm playing catch-up on a few weeks tonight! Week 54 saw the kitchen and utility units arrive onsite now that the kitchen / dining area has been tiled. Fitting of the units was started and spaces are looking good. It had been so long since we picked these that we'd forgotten what they actually looked like!
The first coats of paint were also started this week, with the kiddies getting the only shots of colour at the moment! Other jobs this week included fitting of staircase oak handrails, fitting of the entrance hall Douglas Fir beams and rafters, and the foundations for the pellet store were started.
Pink as requested! |
![]() |
Family bathroom shower and cupboard |
Handrails fitted - just waiting on the glass |
Floor tiled and kitchen starting to take shape |
Utility units going in .... |
Glass ordered so wood beams started for supporting structure |
Foundations for pellet store |
Goodbye septic tank ... |