Hi folks,
Well, another week in ... 58 down and
counting! This has been quite a
rewarding week to see because it actually feels like we can see the end in
sight now. I think the fact that
the deck is now finished, lights/switches/sockets have turned up onsite, more floors going down and the store is nearly
complete, means that we are soon to be focusing on the details and finishes now rather than building stuff (ignoring the breezy entrance of course!).
You need to see the photo below for the wacky double glazing ... quite possibly the coolest windows I've ever seen! I see how the template was made, but have no idea how these units were actually made. These are getting fitted in next week.
We also played around with landscaping some
more this week so think we’re almost there on that front. Cedar hot tub has been ordered (see
rustictubs.com), so space has been made for that bad boy next to the river!
 |
Entrance getting ready for the glass - drainage and tiles |
 |
Edges for drive way and paths going in |
 |
Store coming together nicely (still needs extra cladding) |
 |
Decked area looking really fab now |
 |
A view West, upstream along the Feugh bank |
 |
Wood flooring arrived - Kahrs Oak |
 |
Our lovely Caithness slate down in the utility |
 |
Caithness slate for the entrance hall |
 |
The coolest windows ever for guest room - check out the profile!! |
 |
View from dining space to the deck |
 |
Occhio Piu Alto LED lights ... a wee treat for main extension |
 |
Another Occhio treat for the granite wall inside the Mill - called Puro, these are so cool! |
 |
One of the external lights |