I've been slack with my updates for last week ... a bit too busy to sit down at the computer! Week 9 didn't see a huge amount of progress to be honest. The first floor joists were pretty much complete during the week, but other than that, nothing much to report. We've been at a stalemate trying to resolve some issues around how to rebuild the granite opening and also on some other tender related things. It is all resolved now so hopefully the next weeks blog will have more progress to show.
See ya!
Hardcore now all filled in and compacted |
Looking up to the other first floor bedroom floor |
Structure looking more visible now - pipes are for bathrooms |
![]() |
1st floor ends - then into full height hallway |
A view from above ... |
Another view from above ... |
Opening will be reformed within the next week or two |
View from West side again |
![]() |
Sun streaming in |
![]() |
A lovely sunny evening :-) |
No comments: