Hi folks,
This and the next 3 posts will be catch up posts as I've been away on business! This one is for w/c 23rd May.
This was a pretty slow progress week again - hampered by bad weather and various project issues that I won't bore you with! All that was really achieved this week was the erection of the steel structural ridge beam for the roof. This is now in position and fixed - not in the right place, but close enough!
 |
A view from the North - ridge beam now in! |
 |
Beam fixed into West gable end |
 |
The hole is still there! |
 |
Not much happened externally |
 |
Starting to ready some drain lines in the hall and utility wing |