Catching up tonight on a couple of weeks activity for the blog! During week 46 the downstairs bedrooms were fitted with plasterboard and there was some more progress on the roof, but hey ho, no glass therefore still not water tight! Rooms are now all formed inside the Mill. This week also saw our builder sort out the installation details with our supplier for the biomass boiler. This means we are now going to go to local planning for another small extension to the office/utility block so that we can house our 6 ton pellet hopper as close as possible for running the wood pellet vacuum feed pipes. Here's hoping we get it through without hassle! Our track record to date isn't exactly speedy on that front!!
Outside, the outer beams for the decking were fitted ... nice space.